PSN-L Email List Message
Subject: concrete piers
From: ian@...........
Date: Tue, 05 Nov 2002 12:19:33 +0000 (GMT)
having read the article on installing seismometers, 
http://www.seismo.berkeley.edu/seismo/bdsn/instrumentation/guidelines.html ,
I'm a little unclear on one aspect and would appreciate some advice.
The article states that a 4 inch gap should be left around the base of the 
pier.  What about the rest of the pier?
Also, the 4 inch gap seems to be filled with insulation.  Won't this cause the 
pier to move with the insulation/surrounding ground?
I'll be building on clay soil.  How deep should I go (within reason!) and are 
there any other tips for clay?
TIA
Ian Smith